Microsoft Office Project Image
Project Start Date: Fri 10/26/07
Project Finish Date: Fri 8/15/08

Blended Learning Project - Phase II

ID
Task_Name
DurationStart_DateFinish_DateResource_Names
1
Awareness awareness of technology and importance to the BIS mission
60 days?Fri 10/26/07Thu 1/17/08 
2
Rich media digital story
27 days?Fri 10/26/07Mon 12/3/07EF
3
Blended Learning/Web 2.0 Week
5 days?Mon 12/3/07Fri 12/7/07GK,EF,CM
4
Blackboard/Elluminate Live! Workshops for faculty
58 days?Fri 10/26/07Tue 1/15/08GK,EF,CM
5
Institutional awareness TBD
60 daysFri 10/26/07Thu 1/17/08GK,DP
6
Student awareness TBD
60 daysFri 10/26/07Thu 1/17/08GK,EF
7
Interest intrigued by potential
58 days?Fri 10/26/07Tue 1/15/08 
8
"Elluminati" e-mail discussion forum
21 daysFri 10/26/07Fri 11/23/07GK,EF
9
Design & implementation
21 daysFri 10/26/07Fri 11/23/07GK,EF
10
NPR-style podcasts by experts (3-5 minutes)
58 days?Fri 10/26/07Tue 1/15/08GK,EF
11
Ed Berger
1 day?Fri 11/23/07Fri 11/23/07 
12
Charlotte
1 day?Fri 10/26/07Fri 10/26/07 
13
Nanotechnology
1 day?Fri 10/26/07Fri 10/26/07EF
14
Learning Conference
1 day?Fri 10/26/07Fri 10/26/07GK
15
Other - TBD
1 day?Tue 1/15/08Tue 1/15/08EF,GK
16
Elluminate Live! webinars teaching workshops, technology discussions, how-to sessions, etc.
1 day?Fri 10/26/07Fri 10/26/07GK,CM
17
BIS faculty meeting using Elluminate Live!
1 day?Fri 12/14/07Fri 12/14/07GK,DP
18
Blended Learning Website revision
14 days?Fri 10/26/07Wed 11/14/07EF
19
Acceptance tecnology viable --- for others
1 day?Fri 10/26/07Fri 10/26/07 
20
TBD
1 day?Fri 10/26/07Fri 10/26/07 
21
Commitment - technology viable for oneself
211 days?Fri 10/26/07Fri 8/15/08 
22
New adjunct hiring procedures
1 day?Fri 10/26/07Fri 10/26/07GK,DP
23
BIS instructors Blackboard-literate
211 daysFri 10/26/07Fri 8/15/08GK,EF
24
BIS instructors Elluminate-acquainted
211 days?Fri 10/26/07Fri 8/15/08GK,EF
25
BIS courses have Blackboard course shells
1 day?Mon 12/3/07Mon 12/3/07 
26
Revise BIS BB template
1 day?Mon 12/3/07Mon 12/3/07EF
27
Faculty ready to use Blackboard as backup platform
58 days?Fri 10/26/07Tue 1/15/08EF
28
Engagement take steps to create blended courses
211 days?Fri 10/26/07Fri 8/15/08 
29
Faculty members incentivized to develop first blended course
197 days?Thu 11/15/07Fri 8/15/08GK,DP,JN
30
Meeting with Jen Newell
1 day?Thu 11/15/07Thu 11/15/07DP
31
Development efforts
1 day?Fri 8/15/08Fri 8/15/08 
32
Lessons learned - BIS Faculty (Elluminate)
1 day?Mon 12/3/07Mon 12/3/07GK
33
Training
58 days?Fri 10/26/07Tue 1/15/08 
34
Faculty BB training plan
22 days?Mon 12/17/07Tue 1/15/08GK,EF
35
Student BB training plan TBD
21 daysFri 10/26/07Fri 11/23/07EF
36
Faculty Elluminate training plan
21 daysFri 10/26/07Fri 11/23/07EF
37
Student Elluminate training plan
37 days?Fri 10/26/07Mon 12/17/07EF
38
Support
1 day?Fri 10/26/07Fri 10/26/07 
39
Instructional design support (15 hours initially + 2 hours / session ongoing)
1 day?Fri 10/26/07Fri 10/26/07 
40
Elluminate support plan for instructors and students
1 day?Fri 10/26/07Fri 10/26/07 
41
BB support plan
1 day?Fri 10/26/07Fri 10/26/07 
42
Lessons learned debriefs
1 day?Fri 10/26/07Fri 10/26/07 
43
Transition plan for moving faculty courses from Blackboard to Sakai
1 day?Fri 10/26/07Fri 10/26/07